Consider the effect that the choice of a single word can have upon the success or failure of a standard.The standard is DO-278A, and the word is, ‘approve’. DO-278 is the ground worlds version of the aviation communities DO-178 software assurance standard, intended to bring the same level of rigour to the software used for navigation and air traffic management. There’s just one tiny difference, while DO-178 use the word ‘certify’, DO-278 uses the word ‘approve’, and in that one word lies a vast difference in the effectiveness of these two standards.

DO-178C has traditionally been applied in the context of an independent certifier (such as the FAA or JAA) who does just that, certifies that the standard has been applied appropriately and that the design produced meets the standard. Certification is independent of the supplier/customer relationship, which has a number of clear advantages. First the certifying body is indifferent as to whether the applicant meets or does not meet the requirements of DO-178C so has greater credibility when certifying as they are clearly much less likely to suffer from any conflict of interest. Second, because there is one certifying agency there is consistent interpretation of the standard and the fostering and dissemination of corporate knowledge across the industry through advice from the regulator.

Turning to DO-278A we find that the term ‘approver’ has mysteriously (1) replaced the term ‘certify’. So who, you may ask, can approve? In fact what does approve mean? Well the long answer short is anyone can approve and it means whatever you make of it. What usually results in is the standard being invoked as part of a contract between supplier and customer, with the customer then acting as the ‘approver’ of the standards application. This has obvious and significant implications for the degree of trust that we can place in the approval given by the customer organisation. Unlike an independent certifying agency the customer clearly has a corporate interest in acquiring the system which may well conflict with the object of fully complying with the requirements of the standard. Give that ‘approval’ is given on a contract basis between two organisations and often cloaked in non-disclosure agreements there is also little to no opportunity for the dissemination of useful learnings as to how to meet the standard. Finally when dealing with previously developed software the question becomes not just ‘did you apply the standard?’, but also ‘who was it that actually approved your application?’ and ‘How did they actually interpret the standard?’.

So what to do about it? To my mind the unstated success factor for the original DO-178 standard was in fact the regulatory environment in which it was used. If you want DO-278A to be more than just a paper tiger then you should also put in place mechanism for independent certification. In these days of smaller government this is unlikely to involve a government regulator, but there’s no reason why (for example) the independent safety assessor concept embodied in IEC 61508 could not be applied with appropriate checks and balances (1). Until that happens though, don’t set too much store by pronouncements of compliance to DO-278.

Final thought, I’m currently renovating our house and have had to employ an independent certifier to sign off on critical parts of the works. Now if I have to do that for a home renovation, I don’t see why some national ANSP shouldn’t have to do it for their bright and shiny toys.

Notes

1. Perhaps Screwtape consultants were advising the committee. 🙂

2. One of the problems of how 61508 implement the ISA is that they’re still paid by the customer, which leads in turn to the agency problem. A better scheme would be an industry fund into which all players contribute and from which the ISA agent is paid.

No Comments

Be the first to start the conversation!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s